QLD Health

Summary Of Results

TOTAL INVESTMENT

$84,797

ANNUAL SAVINGS

$29,456

RETURN ON INVESTMENT

35%

CO₂ SAVINGS PER YEAR

300 TONNES

QLD Health

Queensland Health – Voltage Power Optimisation

Case Study: Ecosave Energy Savings Project – St George Hospital

St George Hospital Voltage Power Optimisation Project (VPO)

Queensland Health is a dynamic organisation committed to providing a range of services aimed at achieving good health and well-being for all Queenslanders. Through a network of 16 Health Service Districts and the Mater Hospital. Queensland Health delivers a range of integrated services, such as Medical, Surgical, Accident and Emergency, Outpatients, Obstetrics and Gynaecology, Postnatal care, Palliative Care.

ECOSAVE COMPLETED AN ENERGY CONSERVATION PROJECT AT ST GEORGE HOSPITAL WHICH ACHIEVED THE FOLLOWING RESULTS:

As part of the Voltage Power Optimisation project at St George Hospital, a voltage regulation unit (VR unit) was installed and connected to the incoming electricity supply to the site’s main switchboard. The VR unit chosen for this application eliminates excessive voltage spikes whilst maintaining voltage within the required limits. This unit has provided better than expected savings, with no issues or disruption to St George Hospital operations.

In addition to the Voltage Regulator the following solutions were also installed:

  • Air conditioning temperature set point adjustments
  • Air conditioning energy saving modules
  • Lighting refurbishments to fluorescent fittings using energy efficient components
  • Lighting replacements with energy efficient lights
  • Re-lamping of existing light fittings with energy efficient lamps

The following graph shows the site voltage variations before and after the installation of the VR unit.

site voltage variations graph

Several other energy savings initiatives were also carried out by Ecosave for Queensland Health – see Case Study: Energy Savings Project – Queensland Health 

Menu